The Lake Trafford Road Corridor Project, which included lighting design for Lake Trafford Road from SR 29 (15th Street) to Ann & Ski Olesky Park and a portion of Carson Road, has been closed due to unresolved utility conflicts associated with planned roadway and sidewalk improvements. Work was suspended on April 10, 2024, to allow coordination with other infrastructure projects and address potential conflicts involving streetlight pole locations and water and wastewater utilities.
The design effort was approximately 43% complete at the time work was suspended. Jacobs Engineering’s contract expired on August 24, 2026, and was not extended.
Although the lighting improvements remain a priority for the Immokalee CRA to enhance community safety, any future efforts to advance the project will need to be undertaken in a new capacity and will be contingent upon resolution of the utility conflicts, coordination with the applicable agencies, and identification of available funding.